BRT Transbrasil works: new traffic closures starting this Friday, the 21st

Published on 21/08/2020 - 16:09 | Updated
  • Home/
  • /
  • BRT Transbrasil works: new traffic closures starting this Friday, the 21st
Main alternative route is the Red LineThe main alternative route is the Red Line - Disclosure/City Hall

The City of Rio, through CET-Rio, informs about the NEW closures that will occur to make the TRANSBRASIL works viable. The extended interventions and the old ones, which are still in progress, will also be presented.

The operations will involve the participation of traffic operators, including CET-Rio agents, the Municipal Guard and outsourced workers, who will work to maintain fluidity, guide drivers and set up roadblocks during the interventions. In addition, specific signage will be installed to guide and alert drivers.

NEW CLOSURES WITH GREATER ROAD IMPACT OR CONTINUOUS

1. WALKWAY HEIGHT 13, RAMOS Start: Friday (21/08)

End: Sunday (23/08)
Between 22:21 p.m. on Friday (08/23) and 23:08 p.m. on Sunday (2/1), the operation to build the drainage network on Av. Brasil, near Ramos, will continue. The work aims to eliminate flooding points in the region. To make the procedure viable, it will be necessary to close 13 lanes of the Central lane (right side) and XNUMX lane of the Lateral lane (left side) of Av. Brasil, towards the Center, at the height of walkway XNUMX.

DETOURS: vehicles will be diverted on the lane itself, in the narrow section.

2. CATWALK HEIGHT 21, LUCAS STOP Start: Saturday 22/08

Estimated completion date: 08/09
Starting at 8 am on Saturday (22/08) the operation to build the drainage network on Av. Brasil, near Parada de Lucas, will continue. The work aims to eliminate flooding points in the region. To make the procedure viable, it will be necessary to close 1 lane of the Side lane (left side) of Av. Brasil, towards Deodoro, near Passarela 21. The right lane, which is currently closed, will be opened.

DETOUR: vehicles will be diverted to the right lane, in the narrow section.

3. AV. BRIGADEIRO TROMPOWSKI Start: Saturday 22/08

Estimated completion date: 15/09
Starting at 8 am on Saturday (22/08) the operation to build the drainage network near Ramos will continue. The work aims to eliminate flooding points in the region. To make the procedure viable, it will be necessary to close 1 lane (left side) of Av. Brigadeiro Trompowski, towards Ilha do Governador.

DETOUR: to ensure that vehicles can divert to the right lane, parking will be prohibited along the entire length of the roadworks.

EXPLANATORY PAMPHLETS

Explanatory pamphlets were distributed in the region to inform and guide the population about the work and the prohibition of parking on the road, as illustrated below.

4. CATWALK HEIGHT 20, LUCAS STOP Start: Saturday 22/08

Estimated completion date: 19/09
Starting at 8 am on Saturday (22/08) the operation to build the drainage network on Av. Brasil, near Parada de Lucas, will continue. The work aims to eliminate flooding points in the region. To make the procedure viable, it will be necessary to close 1 lane of the Side lane (right side) of Av. Brasil, towards the Center, near Passarela 20.

DETOUR: vehicles will be diverted to the right lane, in the narrow section.

5. WALKWAY HEIGHT 27, COELHO NETO Start: Saturday 22/08

Estimated completion date: 23/08
Between 22:22 p.m. on Saturday (08/16) and 23:08 p.m. on Sunday (27/XNUMX), the sanitation network will be surveyed on Av. Brasil, near Coelho Neto. To make the procedure possible, it will be necessary to close the loop that connects Av. Brasil, towards Deodoro, near Passarela XNUMX, and Av. Pastor Martin Luther King Júnior. Access for residents will be maintained.

DETOUR: vehicles should follow Av. Brasil to Rua Pedro Jório, access Rua Vitor Frond and follow Av. Pastor Martin Luther King Júnior to Colégio to make the return and continue towards Pavuna.

NEW CLOSURES WITH LESS ROAD IMPACT

The interventions will take place in the direction of the road with less traffic or at night. Therefore, no impact on traffic is expected. The diversions will be carried out on the road itself, in the narrow section.

a. Av. Brasil, at the height of João Paulo Road, Barros Filho Start: Saturday 22/08
Estimated completion date: 22/08
• From 13 pm to 15 pm: closure of 2 lanes of the central road (right side), towards the Center;
• From 15pm to 18pm: closure of 1 lane of flexible pavement (left side) of the central lane, towards the Center.

b. Av. Brasil, height of walkway 27, Coelho Neto Start: Monday 24/08
Estimated completion date: 28/08
• Between Monday (24/08) and Wednesday (26/08), from 22 pm to 4 am (the following day): closure of 2 lanes of the central road, towards Deodoro;
• Between Thursday (27/08) and Friday (28/08), from 22 pm to 4 am (the following day): closure of 1 lane of the central road, towards Deodoro.

c. Av. Brasil, near Passarela 1, Caju Start: Monday 24/08
Estimated completion date: 31/08
• Between Monday (24/08) and 29/08, from 21pm to 5am (the following day): closure of 2 lanes of the side road (right side), towards Deodoro;
• Between Monday (24/08) and 31/08, from 21pm to 5am (the following day): closure of 1 lane of the side road (right side), towards the Center.

d. Av. Brasil, near the bus station Start: Tuesday 25/08
Estimated completion date: 26/08
• Tuesday (25/08) and Wednesday (26/08), from 13 pm to 17 pm: closure of 1 lane of the central lane (right side), towards the Bus Station, between the projection of Rua São Cristóvão and the Bus Station.