City Hall announces new closures for Transbrasil works

Published on 28/08/2020 - 15:10 | Updated on 28/08/2020 - 15:15
  • Home/
  • /
  • City Hall announces new closures for Transbrasil works
Main alternative route is the Red LineThe main alternative route is the Red Line - Disclosure/City Hall

The City of Rio, through CET-Rio, announces the new closures that will be implemented to facilitate the Transbrasil construction work. The operations will involve the participation of traffic operators, including CET-Rio agents, the Municipal Guard and outsourced workers, who will work to maintain fluidity, guide drivers and set up roadblocks during the interventions. In addition, specific signage will be installed to guide and alert drivers.

NEW CLOSURES WITH GREATER ROAD IMPACT

1. PIRANGI STREET, RAMOS Start: Saturday (29/08)
Estimated completion date: 19/09
Starting at 8 am on Saturday (29/08) the operation to build the drainage network on Av. Brasil, near Ramos, will continue. The work aims to eliminate flooding points in the region. To make the procedure viable, it will be necessary:
• Close the side lane of Av. Brasil, towards the center, between Dr. Nunes and Alcameia streets;
• Close the existing switch (from the side to the central lane) located on Av. Brasil, towards the center, between Ruas Alcameia and Luís Câmara;
• Open a temporary switch (from the side lane to the central lane), on Av. Brasil, towards the center, between Dr. Nunes and Pirangi streets;
• Open a temporary switch (from the central to the side lane), on Av. Brasil, towards the center, between Luís Câmara and Felizardo Fortes streets.

CURRENT SITUATION

FROM 8 AM ON SATURDAY (29/08)
Side Track Closure and Switch Modifications

DETOURS: vehicles will be diverted to the central lane, after Rua Dr. Nunes, and may return to the side lane at Rua Luís Câmara.

BUS STOP: the bus stop located between Pirangi and Alcameia streets will be deactivated during the intervention period. Users will be able to choose the bus stops located at walkways 13 or 14.

 

2. WALKWAY HEIGHT 27, COELHO NETO Start: Saturday (29/08)

Estimated completion date: 30/08

Between 22:29 p.m. on Saturday (08/16) and 30:08 p.m. on Sunday (27/XNUMX), the sanitation network will be surveyed on Av. Brasil, near Coelho Neto. To make the procedure possible, it will be necessary to close the loop that connects Av. Brasil, towards Deodoro, near Passarela XNUMX, and Av. Pastor Martin Luther King Júnior. Access for residents will be maintained.

DETOUR: the access road to Estrada João Paulo remains closed. Therefore, vehicles heading to Av. Pastor Martin Luther King Júnior or wishing to return to the city center must continue to Estrada do Camboatá to make the return trip.

3. WALKWAY HEIGHT 28, COELHO NETO Start: Saturday (29/08)

Estimated completion date: 30/08

Between 23pm on Saturday (29/08) and 7am on Sunday (30/08) the beam lifting operation will take place for the road widening of Av. Brasil, in Coelho Neto. To make the procedure viable, it will be necessary:

• Between 23pm on Saturday (29/08) and 7am on Sunday: close 2 lanes (right side) of Av. Brasil, towards Centro, between Rua Cajurana and Passarela 27;
• Between 23pm on Saturday (29/08) and 7am on Sunday: completely close Av. Pastor Martin Luther King Júnior, towards Colégio, in the section under Av. Brasil;
• Between 23pm on Saturday (29/08) and 7am on Sunday: block access from Av. Brasil to Av. Pastor Martin Luther King Júnior, towards Colégio;
• From 0:0 to 40:30 on Sunday (08/1): close 27 lane (left side) of Av. Brasil, towards Deodoro, at Passarela XNUMX.

 

MAIN PROHIBITIONS

FROM 23 AM ON SATURDAY (29/08)
Closure of Av. Brasil and Av. Pastor Martin Luther King Júnior

To ensure operational safety during the lifting of the beam, Av. Brasil, towards the center, will be completely closed for 10 minutes.

CHANGE IN ROAD FLOW: Rua Cajurana, between Rua Guassupi and Rua Aceguá, will operate in two-way traffic to facilitate the detour on the neighborhood's internal streets.

DEVIATIONS

Vehicles coming from Av. Brasil heading to the center
They will be diverted to the left lane (hard surface).

Vehicles coming from the side road to Av. Brasil heading to Av. Pastor Martin Luther King Júnior, towards Colégio
They will be diverted via Rua Bagé, Guassupi, Cajurana and Aceguá to access Av. Pastor Martin Luther King Júnior.

Vehicles coming from Av. Pastor Martin Luther King Júnior bound for the College or wishing to return to the center
They will be diverted via the side road to Av. Brasil towards Deodoro and should continue to Estrada do Camboatá to make the return.

4. HEIGHT OF SÁ FREIRE STREET, CAJU Start: Monday (31/08)

Estimated completion date: 12/09

Starting at 8 am on Monday (31/08), construction of the lane divider on Av. Brasil in Caju will begin. To make the procedure viable, it will be necessary to close 1/2 lane of the central lane (right side) and 1/2 lane of the side lane (left side) of Av. Brasil, towards Deodoro, at the height of Rua Sá Freire, Caju. The detours will be made on the lane itself, in the narrowed section.

 

NEW CLOSURES WITH LESS ROAD IMPACT

The interventions will take place in the direction of the road with less traffic or at night. Therefore, no impact on traffic is expected.

1. Av. Brasil, at the height of João Paulo Road, Barros Filho Start: Saturday (29/08)
Estimated completion date: 29/08
• From 13 pm to 15 pm: closure of 2 lanes of the central lane (right side), towards Deodoro;
• From 15pm to 17pm: closure of 1 lane of flexible pavement (left side) of the central lane, towards Deodoro.
DETOUR: vehicles will be diverted on the lane itself, in the narrow section.

2. Av. Brasil, near Passarela 23, Irajá Start: Monday (31/08)
Estimated completion date: 01/09
• From 22 pm to 4 am the following day: closure of 1 lane of the side road, right side, towards Deodoro.
DETOUR: vehicles will be diverted on the lane itself, in the narrow section.

3. Between Ramos and Cordovil Start: Wednesday (02/09)
Estimated completion date: 16/09
• From 23pm to 5am the following day: total closure of the central lane of Av. Brasil, towards Deodoro, between Passarela 9 and Passarela 19.
DETOUR: vehicles will be diverted to the side lane.

  • August 28th, 2020